Alley Way Sealing Project

Potomac Greens Road (Alley Way) Project

The road project is quickly approaching. Please see the dates and map as to when your area will be affected. The project is to take place in the alleys behind the townhomes.

We ask for your patience and understanding while we work in your neighborhood.
Your property will be broken down into 2 sections, as shown on the accompanying map, and is scheduled for the dates listed below:

May 30th – Sealcoating Section 1 – BLUE section on map (NO PARKING)
June 1st – Sealcoating Section 2 – YELLOW section on map (NO PARKING)

Each Sealcoating Section will close at 7:00 am and will remain closed for 24 hours.

Things to Remember

Parking – All vehicles must be out of the affected parking areas by 7:00 AM on days when work is scheduled. It might be a good idea to move your vehicles the night before the scheduled date.

Driveway/Garage Parking – You may park in your garage while they are working, but please realize that the roads in each section will be closed and any vehicles parked in your garage will be blocked in for 24 hours. You cannot pull out of your driveway once we have begun sealcoating.

Vehicular Traffic – No traffic will be allowed on the roadways during the time your section is closed. Please abide by all barricades and signs; they are for your safety!

Pedestrians/Pets – Please stay off of the freshly sealed asphalt while the section is closed. Walking through wet sealer will result in tracking of the product onto concrete sidewalks and even into your homes. This is costly to clean and is not the responsibility of Dominion Paving & Sealing or the Community Association.

Weather – All dates are weather dependant. In the event of rain, we will be forced to cancel the project for that day. You will be notified as to when your parking lot has been rescheduled.