Metrorail Station Construction 8/17/2021 Update

North Pavilion.  PYC has installed two of the three sections of the 210-foot pedestrian bridge that will connect the North pavilion to the Knuckle (photos 1-3).  Additional bridge trusses arrived on-site on Monday, August 16, 2021.

South Pavilion. PYC has nearly completed the substructure for the South Pavilion (photo 4).  A 520-foot pedestrian bridge will connect the South pavilion to the Knuckle.

Pile Driving.  WMATA anticipates PYC will begin driving the 125 piles required for the 1000-foot retaining wall along the east side of our access route to the Metrorail station entrance in October 2021.

update courtesy of Steve Crime, PG’s neighborhood liaison to PYMIG.