PYMIG will hold a virtual meeting via Zoom on Monday, August 24, from 7-9 pm. You can sign-up to attend the meeting here. update courtesy of Steve Crime, PG’s neighborhood liaison to PYMIG.
Metrorail Station Construction 8/17/2021 Update
North Pavilion. PYC has installed two of the three sections of the 210-foot pedestrian bridge that will connect the North pavilion to the Knuckle (photos 1-3). Additional bridge trusses arrived on-site on Monday, August 16, 2021. South Pavilion. PYC has…
PYC Overnight Noise Variance for Aug. 13 – 16
Communication from Potomac Yard Constructors & the City of Alexandria Reference: Potomac Yard Metrorail Station | Contract No. FQ16146 Subject: Noise Variance Permit – August 2021 – Communications and Signal Upgrades Residents: Potomac Yard Contractors (PYC) has been issued a…
Changes to Community’s Events Schedule, Movie Night + survey reminder
Dear PG neighbors– In light of the shifting COVID landscape here in Alexandria, the PG Social Committee has made some changes to our community’s event schedule over the next couple months. The Rustico happy hour that was scheduled for this…
Stormwater Pond Remediation Complete
Dear PG neighbors— The PG HOA Board is pleased to announce that remediation work on the stormwater pond, which started the week of July 12th and was the first major remediation work performed on the pond in its 20+ years,…
New Metro Shuttle Survey
PG neighbors– Please take a moment to complete this new, more detailed survey regarding the Braddock Rd. Metro shuttle. As you’ll see, we’re now asking for information about not only whether you’ll be using the shuttle in the near future but when.…
Metrorail Station Construction Update 7/26/2021
Daphne Kott (City Staff) just notified us that WMATA will send out a press release this afternoon around 3 pm announcing that the Potomac Yard Metrorail Station opening will be delayed six months until September 2022. WMATA provided the supplier…
Stormwater Pond Remediation Work
Dear PG neighbors– Work has begun on the stormwater pond remediation project to bring it into functioning order as a dry pond in compliance with Virginia Department of Environmental Quality (DEQ) standards. The shared-use stormwater pond on the southeast corner…
PYC Overnight Noise Variance for 7/23-26
The following letter was just shared with Steve Crime, PG’s neighborhood liaison to PYMIG. June 30, 2021 Reference: Potomac Yard Metrorail Station Contract No. FQ16146 Subject: Noise Variance Permit – July 2021 – Communications and Signal Upgrades Residents: Potomac Yard…
PYMIG Notes (Video Update) – June 28, 2021
The PYMIG just posted a video update of Metrorail Station construction for June 2021. The purpose of the video was for the builders (Potomac Yard Constructors or PYC) to discuss the Metrorail station’s progress and address the future construction schedule. …