Potomac Yard Constructors (PYC) has been issued a noise variance permit for night work as described below. The scope of work consists of the assembly and erection of the pedestrian bridge across WMATA and CSX roadways (tracks). This work is…
Metrorail Station Construction Update 2/17/21
This past weekend, the builders intended to install the pedestrian bridge from Potomac Yard to the Metrorail station and install duct banks under the WMATA tracks to connect the AC switchgear building to the station. Work on the pedestrian bridge…
Metrorail Station Construction Update – Weekend Work – 2/12/2021
We were told in earlier PYMIG meetings that the builders planned to install the Metrorail Station’s pedestrian bridge from the knuckle to the mezzanine (crossing over the CSX and WMATA tracks) over President’s Day weekend. Due to possible inclement weather,…
Paint Disposal
Many of you may have noticed garbage trucks spilling paint in our alleys. This is caused by improper disposal of unwanted cans of paint. The City provides procedures to properly dispose of unwanted cans of oil-based and latex-based paint. The…
Jan. 2021 PYMIG Meeting Notes (video update) – 2021-02-04
The PYMIG posted a video update of Metrorail Station construction on February 2, 2020. The video’s purpose was for the builders (Potomac Yard Constructors or PYC) to discuss the Metrorail Station’s progress and address the future construction schedule. The video…
PG Parking Permit Survey – 02/02/2021
As the Potomac Yard Metro project continues, the Board is considering applying through the City to designate Potomac Greens as a residential parking permit district. This would allow PG residents to purchase permits and park without issue on our neighborhood…
Start-of-Year Requests, Surveys, Reminders – 1/27/2021
With the new year, the Board has the following reminders and requests for info. 1. Homeowners, please remember to pay your monthly dues and email Christie Beruete (cberuete@sentrymgt.com) with questions. If COVID has affected your ability to pay your dues, please reach…
PYMIG Jan 25, 2021 Meeting Canceled – 1-24-2021
The City has canceled the virtual PYMIG meeting scheduled for Monday, January 25, 2021. The City will post a construction update video on the PYMIG page in lieu of the meeting. Update courtesy of Steve Crime – PG neighborhood’s PYMIG…
Metrorail Station Construction Jan.17, 2021 Update – 1/17/21
This update contains the latest Metrorail station construction photos. The majority of the steel frame for the North entrance pavilion (Potomac Yard side) is now in place (photo 1). The builders completed installing forms for the Metrorail Station’s mezzanine concrete…
PYMIG 12-28-20 Meeting Notes & Video Update
The PYMIG posted a video update of Metrorail Station construction on December 28, 2020. The video’s purpose was for the builders (Potomac Yard Constructors or PYC) to discuss the Metrorail Station’s progress and address the future construction schedule. The video…